When they give heating in Yakutsk in 2015

click fraud protection

How does Yakutsk prepare for the heating season 2015?

When the heating in Yakutsk is switched on, all repairs must be completed. At present, the degree of preparation of heating mains, boiler houses, and also objects of housing and social sphere makes 99%.And this means that soon Yakut people will be pleased with the warmth.

In Yakutsk waiting for the activation of heating

During the summer period, work was carried out on the washing of central heating systems. Not all districts of the city managed the companies conscientiously fulfill their duties. Repairs of elevator units, as well as warming of central heating networks, have been carried out. When in Yakutsk will give heating, all acts of readiness of objects of housing stock. Today, the resource-supplying companies have already issued most of the documents.

The heating system in Yakutsk is almost ready to start

Repair campaign in the summer period provided for the replacement of 98 boilers, 215 pumps, as well as more than 40 units of burner parts. Major overhaul of thermal insulation of engineering networks was carried out. The exact date of heating in 2015 is already known. The head of the city at a meeting on September 10 called the date - September 14.Social institutions have already received warmth in this regard. The turn of housing and communal services has come. Until early October, all objects of the city should be connected to the heating.

In apartments Yakutsk begins to cool down

What does the heat supply schedule depend on?

The timing of the inclusion of heating systems in Yakutsk depends on a number of conditions, the main of which are:

  • availability of funds for timely start of heating;
  • compliance with the timing of repair and maintenance work with the system.

The city administration of Yakutsk has allocated enough money in repair and maintenance of heating systems in 2015 to complete the preparation for the heating season in time.

Today, 99% of consumers are prepared for the start of heating. Repair and preventive measures are carried out exactly in time.

Priority of heating supply in Yakutsk

Traditionally, the first institutions of heat will receive social institutions:

  • hospitals;
  • children's homes;
  • schools;
  • kindergartens.

After they are provided with heat, heating systems will be launched in residential buildings. The latter will connect to the heat of industrial premises.

Optimal temperature in a residential area

If you have any doubts about the quality of housing services in heating systems, make a temperature measurement in the premises of the apartment. The following parameters should be optimal for SANPiN 2.1.2.1002-00:

Room Celsius temperature
optimum acceptable
Living rooms 20-22 18-24
Kitchen 19-21 18-26
WC 19-21 18-26 18-26 16-18 14-20
Storage compartments 16-18 12-22

What to do if the heating was not given to

Find out who you have a contract for the supply of heat. It can be either a management company or a heat utility directly. There you can request that you perform a clearing for improper provision of the service.

By law, heating can be turned off for a month for 24 hours( total for all days).At the same time, there can be no more than 16 hours of continuous heat( if in residential premises +12 and above), no more than 8 hours( if at home 10-12 degrees of heat) and no more than 4 hours( if the temperature is 8-10 degrees).

If these general rules are not met, for each hour of failure to provide services( the total amount for the entire period), heating fees will decrease by 0.15%.