The procedure for obtaining technical specifications and connecting any facility to the power supply in the Russian Federation is regulated by the "Rules technological connection... ", adopted by the Government of the Russian Federation No. 861 of December 27, 2004, the last changes to which were made in 2017. This document defines the regulations on how to get the opportunity to connect to electricity for individuals and legal entities, are consumers, as well as entities engaged in the production and distribution of electricity - power plants and power grid enterprises. Consider the procedure for obtaining technical specifications for the power supply of a private house, garage, land plot and other objects owned by a private or legal entity.
Content:
- The established procedure for obtaining technical specifications
- What documents are needed to obtain a technical specification?
The established procedure for obtaining technical specifications
Clarity should be clarified first. In accordance with the rules in force in the Russian Federation, technical conditions form an integral part of the contract for technological connection, that is, technical specifications (technical conditions) are not an independent document, and their receipt without a contract not provided. In order to be able to connect the power plant to electricity, the following steps must be completed:
- Submission of an application for concluding a contract and obtaining technical conditions to a network organization.
- Signing an agreement regulating the legal and technical aspects of technological connection.
- Fulfillment of technical conditions and other clauses of the contract required in order to be able to connect to electricity.
- Obtaining a permit to connect to the power supply of the Applicant's facilities, issued by the State Energy Supervision Authorities.
- Connection of the Applicant's facilities, carried out by the network organization in accordance with the technical specifications.
- Drawing up an act of the established form, certifying the completion of the connection in accordance with the technical conditions.
The above procedures are necessary in the following cases:
- When it is necessary to obtain technical conditions for connecting a new facility to the power supply.
- With an increase in the volume of the maximum power of the operating facility.
- When changing the power supply scheme. For example, if you need to get a different category of power supply reliability, change the point of connection of the object.
The application is submitted to the grid company whose power supply facilities are closest to the Applicant's site. The proximity of energy facilities determines lighter technical conditions that allow access to electricity. The application form can be either paper, sent by mail, or electronic, that is, it can be submitted via the Internet, on the website of the organization that provides electricity. A sample application to be filled out can be obtained by downloading the annex to the Rules.
The grid company that received an application for concluding a contract and obtaining technical specifications (TU) for connecting to electricity is obliged within 15 days from the date of receipt of the application send to the applicant a paper version of the completed and signed contract in duplicate and the technical specifications, which are an integral part of this document. This obligation also applies if the applicant used the Internet to submit the application and completed it on the company's website.
If the technological connection to electricity is carried out in accordance with an individual power supply project, signed the version of the contract and technical conditions are sent to the applicant within three days from the date of approval of the cost of the technological connections. The approval of the cost of connecting to electricity is carried out by a state body authorized to regulate electricity tariffs. In the case when the applicant submits an application for obtaining technical conditions for the temporary connection of electrical installations to network, the network company sends a draft agreement and technical conditions to him within ten days from the date of submission applications.
In the case when the technical conditions for connecting electricity must be agreed with the System Operator, the term preparation of the draft contract and technical specifications (TU), can be extended by the network company for the time required to obtain such approvals. In this case, the grid company informs the applicant about it. Sending documents in this option is carried out within three days from the receipt of the necessary approval.
In turn, the applicant who received a signed draft contract from the network organization and technical conditions (TU), must send to her address one copy of the document signed by him within thirty days. If the applicant does not agree with the provisions of the draft sent to him, he must send a reasoned refusal with a protocol of disagreements, which indicates changes to the text of the contract and technical conditions (TU), the introduction of which is necessary his opinion. All this must be done within the same thirty days.
After the contract for technological connection for the supply of electricity is concluded, the network organization within two days notifies this of the market entity through which the applicant is going to gain access to electricity to supply the facility, and conclude the appropriate contract. At the same time, the grid organization sends to the electricity supplier a copy of the contract with the technical conditions, as well as copies of the applicant's documents.
What documents are needed to obtain a technical specification?
According to the rules, in order to be able to connect to electricity, the following documents must be attached to the application:
- Diagram of the location of electrical installations, for which it is necessary to obtain permission to connect to the power supply.
- Electrical diagram (single-line) of the applicant's networks. The requirement applies only to networks of 35 kV and above.
- A list of electrical installations with an indication of their capacity. Refers to devices that can be connected to emergency control circuits.
- A copy of the title deed of ownership related to the connectable object.
- For legal entities it is necessary to obtain an extract from the Unified State Register of Legal Entities.
For individuals applying for the conclusion of a contract and obtaining technical specifications for the connection of electrical installations with a capacity of not more than 15 kW, intended for needs not related to the operation of the business, the following must be provided data:
- Full name and passport data of the applicant, or data of another document that can verify the identity of the applicant in accordance with the current laws of the Russian Federation.
- Document confirming the applicant's place of residence.
- The maximum value of the requested power of electrical installations that they are able to obtain at the applicant's facility.
The contract for connection to electricity contains a list of technical measures, the implementation of which is mandatory for the implementation of electricity. The activities and those responsible for their implementation are listed in the attached technical specifications.
We also recommend watching a video that describes in detail how to get technical conditions for electricity connections:
It is in this order that technical conditions are obtained for the power supply of a summer cottage, house or other object. Now you know what documents you need to prepare in order to receive a technical specification for connecting to electrical networks!