The foundation of TISE( Technology of individual construction and ecology) is a columnar foundation with unusual extended lower supports. It features high bearing capacity, can be produced on any ground. Applicable for the construction of frame, brick houses. Suitable for highly priming soils: it does not move, does not collapse. You can build a foundation of TISE with your own hands.

Contents

  1. Drawings and foundation diagrams of TISE
  2. How to build a foundation of TISE with your own hands?
  3. Building foundation video on TISE technology

Drawings and foundation schemes of TISE

Many owners of suburban areas are interested in what is the foundation of TISE.This type of foundation is similar to a conventional pile foundation. But thanks to the extended lower part of the piles has increased strength. It can be used to build houses near highway roads, railway tracks: vibration from the road will not affect its bearing capacity.

A foundation is made using TISE technology without the use of standard metal sleeves, and pile holes for it are created using a special drill. The bucket is not adjacent to the ground and is 15-20 cm away from it.

How to build a foundation of TISE with your own hands?

The work should begin with the layout of the site. The piles mark the location of the piles along the perimeter of the structure. Further, the supports under the bearing walls are marked. To create an accurate markup, use the water level. Between the correctly posed pegs are threaded, marking the location of the supports. Further, pits are drilled under piles.

For drilling, it is necessary to use a special device - TISE drill. It is additionally equipped with a tilting blade, which allows expansion of the pit.

So that the soil does not crumble during the concreting, a "shirt" made of roofing material is made.

When all pits are drilled, they are poured with concrete. During the concreting, the installation of reinforcement, which is responsible for the strength of the supports, is carried out. To do this, you need to use four bars per pile. They must extend above the ground level by approximately 25 cm.

The baying is then carried out - a careful dipping and lifting in the raw solution of the reinforcement. This will remove excess air bubbles.

After piling, they are coated with a mastic for waterproofing.

Previously harvested sand is distributed level with the edges of the finished piles. Further construction of the TISE foundation is carried out according to the following instructions:

1. Threading is carried out for the installation of the grillage formwork.

2. The formwork is installed, the boards are connected to each other.

3. The inside of the shields is covered with a film.

4. In addition, the formwork is fastened with studs, for which the sleeves are dressed as sleeves.

5. The armature is unfolded and tied( 4 twigs of 12 mm reinforcement bars from above and below).

6. Formwork is poured.

A hairpin can be removed one day after the solution is poured. To fully grasp the grillage it will take another 10 days, then the shields are removed. Sand under grillage can be removed and put boards of flat slate on both sides.

At this stage, the base preparation will be completed. But for more information before work, you need to not only learn how to make the foundation of TISE, but also visually assess the complexity of the work. Therefore, you should view photos and video materials on the features of the foundation preparation and understand the attached instructions.